Berri Oilfield Development Project
Installation at the Abu Ali Plant and KGP, as part of the Berri Development Project in the Kingdom of Saudi Arabia.
- Location: Abu Ali Plant, Saudi Arabia
- Main Activities: Elaboration of mechanical equipment datasheets, technical specifications, Material Requisitions (MR), technical alignment of suppliers’ offers, interaction with suppliers for the technical issues (vendor follow-up), check and review of technical Manuals for Air Cooled Heat Exchangers, API and ASME Centrifugal Pumps, Sealless Pumps, Sanitary Pumps.
- Engineering Hours: 5˙500 (3˙000 Pumps + 2˙500 Air Coolers)
- Start-End: 2019/ongoing
- Customer: SAIPEM